Build a cost picture that includes the parts vendors omit.
The goal of this table is a cost picture a finance reviewer will accept, which means including the lines that never appear in a vendor quotation.
|
Cost line |
Typical shape |
Frequently forgotten because… |
|
Authoritative DNS service |
Per zone plus per million queries |
Query volume rises when you shorten TTLs; the two decisions are coupled |
|
Measurement infrastructure |
Per probe or per measurement, plus storage |
It is treated as a project cost, but it must run permanently to be useful |
|
Steering or traffic management |
Per zone, sometimes per decision |
Pricing often scales with query volume, which your own TTL policy controls |
|
Detection tooling and analyst time |
Licence plus the hours spent on alerts |
Analyst time is the dominant cost and never appears in the licence quote |
|
Engineering to build and maintain |
Weeks of internal effort, then ongoing |
Counted at launch, then dropped from the running cost |
|
Model retraining and monitoring |
Recurring compute plus periodic engineering |
Assumed to be zero, which is how models are left to decay |
Two lines dominate in practice. Analyst time is the true cost of any detection capability, and it is invisible in licence pricing. The boss battle in Module 6 illustrated exactly this: a working model imposed a staffing cost nobody had budgeted. Ongoing engineering is the second. It is counted at launch and then quietly dropped, which is how the running cost of an optimisation programme gets understated.
KEY TAKEAWAYÂ Â Your TTL policy is a cost decision. Because most authoritative and steering pricing scales with query volume, and query volume falls roughly in step with longer TTLs, the TTL work from Module 5 reduces spend at the same time as it reduces latency. Improvements that are both faster and cheaper are rare in infrastructure work, so lead with this when you present the business case. It earns credibility for the parts of the programme that do cost money.